FE Civil · PracticeSurveying · Earthwork
Two road cross sections are 30 m apart. Their cut areas are 12 m² and 18 m². Using the average end area method, what is the volume of cut between them?
Worked solution
V = L(A1 + A2)/2 = 30 × (12 + 18)/2 = 450 m³
FE Handbook search: Average End Area
Get 170+ Civil problems like this: start free
Your first 3 days
What’s in your free trial
Chapters 1 and 21 (Structural), every problem with a full worked solution.
Calculator keystrokes for the TI-36X Pro and Casio fx-991EX.
10 Ask Newton questions with the AI tutor.
Your progress saved on any device.
When you’re ready for more
What a pass adds
- All 18 chapters: 11 shared with Mechanical plus 7 Civil-only (Structural, Geotechnical, Water Resources and Environmental, Transportation, Construction, Surveying and Civil Materials).
- 420+ FE-style problems, including 171 Civil-only problems.
- Pro adds a timed full-length 110-problem practice exam, a custom test builder and unlimited Ask Newton.
- Basic and Pro passes for 1, 3 or 6 months. Nothing renews.
- Civil Review Guide and Practice Problems books are in the works.
Start your free 3-day trial
No card required to start.
Explore the Civil track
Free practice problems by topic
Try a free FE-style problem, with the worked solution, in any Civil-only topic.